Calendars

Calendars


 

GIP Study Calendar

GroupDateEvent
 January 4, 2023SIS Group #33 Progression Milestones Due
33January 18, 2023SIS Group #33 Study Period Commences
 May 18, 2023SIS Group #33 Study Period Ends
 May 26, 2023SIS Group #34 Progression Milestones Due
34June 9, 2023SIS Group #34 Study Period Commences
 October 6, 2023SIS Group #34 Study Period Ends
 October 16, 2023SIS Group #35 Progression Milestones Due
35October 30, 2023SIS Group #35 Study Period Commence
 February 27, 2024SIS Group #35 Study Period Ends
 March 5, 2024SIS Group #36 Progression Milestones Due
36March 19, 2024SIS Group #36 Study Period Commences
 July 17, 2024SIS Group #36 Study Period Ends
 July 24, 2024SIS Group #37 Progression Milestones Due
37August 8, 2024SIS Group #37 Study Period Commences
 December 6, 2024SIS Group #37 Study Period Ends
 December 31, 2024SIS Group #38 Progression Milestones Due
38January 1, 2025SIS Group #38 Study Period Commences
 May 1, 2025SIS Group #38 Study Period Ends
 May 8, 2025SIS Group #39 Progression Milestones Due
39May 23, 2025SIS Group #39 Study Period Commences
 September 19, 2025SIS Group #39 Study Period Ends

 

 

DGIP CALENDAR

 GroupDate Event
 April 28, 2023DSIS Group #39 Progression milestones due
39May 12, 2023DSIS Group #39 Study period commences
 August 10, 2023DSIS Group #39 Study period ends
 August 17, 2023DSIS Group #40 Progression milestones due
40August 31, 2023DSIS Group #40 Study period commences
 November 29, 2023DSIS Group #40 Study period ends
 December 6, 2023DSIS Group #41 Progression milestones due
41December 20, 2023DSIS Group #41 Study period commences
 March 19, 2024DSIS Group #41 Study period ends
 March 26, 2024DSIS Group #42 Progression milestones due
42April 09, 2024DSIS Group #42 Study period commences
 July 08, 2024DSIS Group #42 Study period ends
 July 15, 2024DSIS Group #43 Progression milestones due
 43July 29, 2024DSIS Group #43 Study period commences
 October 25, 2024DSIS Group #43 Study period ends
 November 01, 2024DSIS Group #44 Progression milestones due
 44November 18, 2024DSIS Group #44 Study period commences
 February 12, 2025DSIS Group #44 Study period ends
 February 24, 2025DSIS Group #45 Progression milestones due
 45March 10, 2025DSIS Group #45 Study period commences
 June 06, 2025DSIS Group #45 Study period ends

 


Wholesale Market Calendar

DateEvent
Feb 28Annual Generation Output published on OASIS
Mar 15

MP-08 Information Required for Forecasts and Assessments:

18 month and 10-year forecasts due to NSPSO

Apr 3018 Month Forecast & Assessment published on OASIS
Jun 3010 Year System Plans published on OASIS
Sep 15

MP-08 Information Required for Forecasts and Assessments:

18 month forecasts due to NSPSO

Oct 1718 Month Forecast & Assessment published on OASIS
Nov 3

MP-09 Annual Outage Planning:

Preliminary transmission system outage plan posted on OASIS

Nov 18

MP-09 Annual Outage Planning:

Generation Market Participants' preferred plans due to NSPSO
Customer impact review of transmission outage plan due to NSPSO

Nov 30

MP-09 Annual Outage Planning:

NSPSO initial review and feedback due to Transmitter and Generation Market Participants

Dec 17

MP-09 Annual Outage Planning:

Transmitter and Generation Market Participants' revisions to outage plans due to NSPSO

Dec 30

MP-09 Annual Outage Planning:
NSPSO notifications of approval or rejection of annual outage plan due to Transmitter and Generation Market Participants

 

 

 

The information on this page was last reviewed on April 05, 2024.

If there are any issues with OASIS please contact NSPSOAdmin@nspower.ca