Calendars

Calendars


 

GIP Study Calendar

GroupDateEvent
 October 29, 2021SIS Group #30 Progression Milestones Due
30November 15, 2021SIS Group #30 Study Period Commences
 March 15, 2022SIS Group #30 Study Period Ends
 March 22, 2022SIS Group #31 Progression Milestones Due
31April 5, 2022SIS Group #31 Study Period Commences
 August 3, 2022SIS Group #31 Study Period Ends
 August 10, 2022SIS Group #32 Progression Milestones Due
32August 24, 2022SIS Group #32 Study Period Commence
 December 22, 2022SIS Group #32 Study Period Ends
 January 4, 2023SIS Group #33 Progression Milestones Due
33January 18, 2023SIS Group #33 Study Period Commences
 May 18, 2023SIS Group #33 Study Period Ends
 May 26, 2023SIS Group #34 Progression Milestones Due
34June 9, 2023SIS Group #34 Study Period Commences
 October 6, 2023SIS Group #34 Study Period Ends
 October 16, 2023SIS Group #35 Progression Milestones Due
35October 30, 2023SIS Group #35 Study Period Commences
 February 27, 2024SIS Group #35 Study Period Ends
 March 5, 2024SIS Group #36 Progression Milestones Due
36March 19, 2024SIS Group #36 Study Period Commences
 July 17, 2024SIS Group #36 Study Period Ends

 

 

DGIP CALENDAR

 GroupDate Event
 February 8, 2022DSIS Group #35 Progression milestones due
35February 23, 2022DSIS Group #35 Study period commences
  May 24, 2022DSIS Group #35 Study period ends
 May 31, 2022DSIS Group #36 Progression milestones due
36June 14, 2022DSIS Group #36 Study period commences
 September 12, 2022DSIS Group #36 Study period ends
 September 19, 2022DSIS Group #37 Progression milestones due
37October 3, 2022DSIS Group #37 Study period commences
 December 30, 2022DSIS Group #37 Study period ends
 January 9, 2023DSIS Group #38 Progression milestones due
38January 23, 2023DSIS Group #38 Study period commences
 April 21, 2023DSIS Group #38 Study period ends
 April 28, 2023DSIS Group #39 Progression milestones due
39May 12, 2023DSIS Group #39 Study period commences
 August 10, 2023DSIS Group #39 Study period ends
 August 17, 2023DSIS Group #40 Progression milestones due
 40August 31, 2023DSIS Group #40 Study period commences
 November 29, 2023DSIS Group #40 Study period ends
 December 6, 2023DSIS Group #41 Progression milestones due
 41December 20, 2023DSIS Group #41 Study period commences
 March 19, 2024DSIS Group #41 Study period ends

 


Wholesale Market Calendar

DateEvent
Feb 28Annual Generation Output published on OASIS
Mar 15

MP-08 Information Required for Forecasts and Assessments:

Forecasts due to NSPSO

Apr 3018 Month Forecast & Assessment published on OASIS
Jun 3010 Year System Plans published on OASIS
Sep 15

MP-08 Information Required for Forecasts and Assessments:

Forecasts due to NSPSO

Oct 1718 Month Forecast & Assessment published on OASIS
Nov 3

MP-09 Annual Outage Planning:

Preliminary transmission system outage plan posted on OASIS

Nov 18

MP-09 Annual Outage Planning:

Generation Market Participants' preferred plans due to NSPSO
Customer impact review of transmission outage plan due to NSPSO

Nov 30

MP-09 Annual Outage Planning:

NSPSO initial review and feedback due to Transmitter and Generation Market Participants

Dec 17

MP-09 Annual Outage Planning:

Transmitter and Generation Market Participants' revisions to outage plans due to NSPSO

Dec 30

MP-09 Annual Outage Planning:
NSPSO notifications of approval or rejection of annual outage plan due to Transmitter and Generation Market Participants

 

 

 

The information on this page was last reviewed on May 17, 2023.