GIP Study Calendar
| Group | Date | Event |
|---|---|---|
| May 26, 2023 | SIS Group #34 Progression Milestones Due | |
| 34 | June 9, 2023 | SIS Group #34 Study Period Commences |
| October 6, 2023 | SIS Group #34 Study Period Ends |
| October 16, 2023 | SIS Group #35 Progression Milestones Due | |
| 35 | October 30, 2023 | SIS Group #35 Study Period Commence |
| February 27, 2024 | SIS Group #35 Study Period Ends |
| March 5, 2024 | SIS Group #36 Progression Milestones Due | |
| 36 | March 19, 2024 | SIS Group #36 Study Period Commences |
| July 17, 2024 | SIS Group #36 Study Period Ends |
| July 24, 2024 | SIS Group #37 Progression Milestones Due | |
| 37 | August 8, 2024 | SIS Group #37 Study Period Commences |
| December 6, 2024 | SIS Group #37 Study Period Ends |
| December 16, 2024 | SIS Group #38 Progression Milestones Due | |
| 38 | January 1, 2025 | SIS Group #38 Study Period Commences |
| May 1, 2025 | SIS Group #38 Study Period Ends |
| February 20, 2025 | SIS Group #39 Progression Milestones Due | |
| 39 | March 6, 2025 | SIS Group #39 Study Period Commences |
| July 4, 2025 | SIS Group #39 Study Period Ends |
| June 13, 2025 | SIS Group #40 Progression Milestones Due | |
| 40 | June 27, 2025 | SIS Group #40 Study Period Commences |
| October 25, 2025 | SIS Group #40 Study Period Ends |
| October 8, 2025 | SIS Group #41 Progression Milestones Due | |
| 41 | October 22, 2025 | SIS Group #41 Study Period Commences |
| February 19, 2026 | SIS Group #41 Study Period Ends |
DGIP CALENDAR
| Group | Date | Event |
|---|---|---|
| April 28, 2023 | DSIS Group #39 Progression milestones due | |
| 39 | May 12, 2023 | DSIS Group #39 Study period commences |
| August 10, 2023 | DSIS Group #39 Study period ends | |
| August 17, 2023 | DSIS Group #40 Progression milestones due | |
| 40 | August 31, 2023 | DSIS Group #40 Study period commences |
| November 29, 2023 | DSIS Group #40 Study period ends | |
| December 6, 2023 | DSIS Group #41 Progression milestones due | |
| 41 | December 20, 2023 | DSIS Group #41 Study period commences |
| March 19, 2024 | DSIS Group #41 Study period ends | |
| March 26, 2024 | DSIS Group #42 Progression milestones due | |
| 42 | April 09, 2024 | DSIS Group #42 Study period commences |
| July 08, 2024 | DSIS Group #42 Study period ends | |
| July 15, 2024 | DSIS Group #43 Progression milestones due | |
| 43 | July 29, 2024 | DSIS Group #43 Study period commences |
| October 25, 2024 | DSIS Group #43 Study period ends | |
| November 01, 2024 | DSIS Group #44 Progression milestones due | |
| 44 | November 18, 2024 | DSIS Group #44 Study period commences |
| February 12, 2025 | DSIS Group #44 Study period ends | |
| February 24, 2025 | DSIS Group #45 Progression milestones due | |
| 45 | March 10, 2025 | DSIS Group #45 Study period commences |
| June 06, 2025 | DSIS Group #45 Study period ends | |
| June 13, 2025 | DSIS Group #46 Progression milestones due | |
| 46 | June 30, 2025 | DSIS Group #46 Study period commences |
| September 26, 2025 | DSIS Group #46 Study period ends | |
| October 10, 2025 | DSIS Group #47 Progression Milestones Due | |
| 47 | October 24, 2025 | DSIS Group #47 Study Period Commences |
| January 22, 2026 | DSIS Group #47 Study Period Ends |
| February 5, 2026 | DSIS Group #48 Progression Milestones Due | |
| 48 | February 19, 2026 | DSIS Group #48 Study Period Commences |
| May 20, 2026 | DSIS Group #48 Study Period Ends |
| June 4, 2026 | DSIS Group #49 Progression Milestones Due | |
| 49 | June 18, 2026 | DSIS Group #49 Study Period Commences |
| September 16, 2026 | DSIS Group #49 Study Period Ends |
| September 30, 2026 | DSIS Group #50 Progression Milestones Due | |
| 50 | October 14, 2026 | DSIS Group #50 Study Period Commences |
| January 12, 2027 | DSIS Group #50 Study Period Ends |
Wholesale Market Calendar
| Date | Event |
|---|---|
| Feb 28 | Annual Generation Output published on OASIS |
| Mar 15 | MP-08 Information Required for Forecasts and Assessments: 18 month and 10-year forecasts due to NSPSO |
| Apr 30 | 18 Month Forecast & Assessment published on OASIS |
| Jun 30 | 10 Year System Plans published on OASIS |
| Sep 15 | MP-08 Information Required for Forecasts and Assessments: 18 month forecasts due to NSPSO |
| Oct 17 | 18 Month Forecast & Assessment published on OASIS |
| Nov 3 | MP-09 Annual Outage Planning: Preliminary transmission system outage plan posted on OASIS |
| Nov 18 | MP-09 Annual Outage Planning: Generation Market Participants' preferred plans due to NSPSO |
| Nov 30 | MP-09 Annual Outage Planning: NSPSO initial review and feedback due to Transmitter and Generation Market Participants |
| Dec 17 | MP-09 Annual Outage Planning: Transmitter and Generation Market Participants' revisions to outage plans due to NSPSO |
| Dec 30 | MP-09 Annual Outage Planning: |
The information on this page was last updated on October 30, 2025.