Current Projects

Current Projects


Tiverton Tower Replacement

Improving service reliability for Long Island and Brier Island

Nova Scotia Power is investing approximately $1.9 million on a project that will increase service reliability and reduce the risk of power outages for more than 600 customers on Long and Brier Islands. The project includes replacing the tower in Tiverton, on Long Island in Digby County, as well as the electrical lines that cross Petit Passage.

The new tower and electrical lines were safely installed between May and July 2019, and the new tower was painted and had its lights installed in August. After the outage is complete and the new electrical lines are energized, the last step in the project is to remove the old tower and lines.

Project update

Nova Scotia Power has encountered an unexpected delay with the project, which is now scheduled for completion in 2020. The delay is due to heavy rains, which occurred in late June 2019 and caused erosion on the hill near the East Ferry substation, to the west of the new wooden poles. The erosion did not occur in the immediate vicinity of the project and initially, Nova Scotia Power did not believe it would impact the timeline for completion. On further examination, we discovered more evidence of soil failure and the need for a full geotechnical study and remediation. By conducting a geotechnical study, we will prevent any possibility that new poles, installed as part of the rebuild project, could be damaged through further erosion. The existing power lines, which currently provide electricity to customers, are at a safe distance from the area where erosion occurred. 

Nova Scotia Power understands how important this project is to the community and its customers. The project is a priority for us, and we’ll move it to completion as soon as possible. 

Once the geotechnical study is complete and has identified the work that’s required to remediate the area, Nova Scotia Power will confirm the project timelines. Specific next steps include:  

  • Fall 2019: complete a geotechnical study, conducted by a third-party expert.
  • Fall / Winter 2019: review the expert’s recommendations and conduct the work that’s required to stabilize the ground impacted by erosion.
  • 2020: energize the new power lines. To safely do this work, a planned power outage will be required. Customers will be notified in advance of this outage and we’ll work with them to identify a time that will reduce impacts to their homes/businesses and local tourism. To avoid impacts during lobster season or during high tourism demands, this may mean the project won’t be complete until mid or late 2020. This timeline will be developed in consultation with customers.
  • 2020: remove the old power lines and tower.

New lines, new lights

The new Tiverton tower now has navigation lights installed — one light on top of the tower, and one light at the mid-point. These lights will flash red at twilight and night-time. Powered by photocells, the lights on the tower are much like the headlights on a car — they may activate during the day if there is heavy fog or cloudy skies.

 

INGONISH LINE REBUILD

Improving line accessibility and outage response time for customers

Nova Scotia Power is working collaboratively with Parks Canada to relocate power lines in the Ingonish area of the Cape Breton Highlands National Park. The work began October 7, 2019 and is expected to be completed n early 2020.

The current power structures are 40 years old and are surrounded by trees that during storms, damage the lines, causing power outages. The new line — to be located between the Ingonish Beach entrance of the Park, the Clyburn River and around the Broad Cove campground — will be moved from forested areas to the roadside. The line rebuild will replace the aging infrastructure, reduce the overall environmental footprint, reduce line exposure to trees, improve line accessibility and improve outage response times.

As part of its project planning, Nova Scotia Power developed a Detailed Impact Analysis (DIA) that outlines the benefits of the work, environmental considerations, mitigation measures and approach to safely completing the project. Parks Canada shared the DIA with the Mi’kmaq of Nova Scotia through the Crown’s Duty-to-Consult process and with the public, through a public engagement process. For a summary of engagement feedback, please visit here.

Nova Scotia Power is committed to protecting the environment and will take steps to ensure the power line work is done in a manner that minimizes impacts on the nearby ecosystem.

During periods of construction, some portions of the Cabot Trail between Ingonish Beach and Clyburn River experience lane reductions and traffic delays are possible.

The Ingonish line rebuild will improve line accessibility and outage response time for customers in Wreck Cove, Ingonish Ferry, South Ingonish Harbour, Ingonish Beach, Ingonish Centre, Neil’s Harbour, Smelt Brook, South Harbour, Dingwall, Cape North, Pleasant Bay, and Meat Cove. It is the sole source of electricity for approximately 2,160 customers and visitors in these communities.

CBH Aerial Lg-edit